Always Part of the Solution

Columbus School Construction

Elementary 

Phase 2 Construction

Columbus Elementary School: We are completed with the summer renovation work and the new 1st grade classroom is complete and operational. The new Library is 100% framed and roofed and we are currently working on the roof framing for the administration and commons area. Classroom framing is set to start in the next two weeks! We are scheduled to pave the new drive lane off 2nd street by the end of the October.

Columbus High School: Summer renovations to the Middle School Commons, weight room, and gym storage are complete! The front entry addition framing is complete and we are currently working on the mechanical, electrical, and plumbing systems. We are scheduled to begin siding middle of October and are on schedule for a December completion!